Please note that the 49th Ward Service Office will be closed from December 20th, 2024 through January 5th, 2025. Additionally, the office will be closed to the public on January 6th and 7th, 2025 for administrative planning.
​
We look forward to serving you in the new year!
Oficina de servicio de barrio
1447 W. Morse Ave
Chicago, IL 60626
PN7342 Updates
March 24, 2023
The contractor has finished the exploratory work. Concrete restoration and patching will continue in the area for at least two weeks.
Crews are still finalizing a date to begin the sewer main project. Once that date has been scheduled, we will share it here.
For more information on the footprint of the project and to review an FAQ, visit the 49th Ward by clicking here.
​
March 17, 2023
The contractor has finished the exploratory work. Concrete restoration and patching will continue in the area for at least two weeks.
Crews are still finalizing a date to begin the sewer main project. Once that date has been scheduled, we will share it here.
For more information on the footprint of the project and to review an FAQ, visit the 49th Ward by clicking here.
​
March 11, 2023
Pre-construction is still wrapping up. Once work is finished, it will take an additional couple of days to demobilize and move equipment stored on the street.
Crews are still finalizing a date to begin the sewer main project. Once that date has been scheduled, we will share it here.
For more information on the footprint of the project and to review an FAQ, visit the 49th Ward by clicking here.
​
March 4, 2023
Our office hosted a community meeting with representatives from the Department of Water Management on Thursday. During that meeting, crews provided an update that the pre-construction work on Lakewood, Wayne, and Magnolia will be finished by the end of next week. Once preconstruction is finished, they will repair the streets, parkways, and sidewalks.
Crews are still finalizing a date to begin the sewer main project. Once that date has been scheduled, we will share it here.
For more information on the footprint of the project and to review an FAQ, visit the 49th Ward by clicking here.
​
February 24, 2023
Construction crews began to mobilize on Magnolia and Lakewood last week to begin pre-construction and corrective work in the area before transitioning to the sewer replacement. This means neighbors might begin to see more equipment and some excavation begin in the area. Crews may post "No Parking" signs in the impacted area as needed during work hours (generally 7 am to 4 pm). Crews will work to preserve as much parking as possible and will only post signs where crews are actively working; parking restrictions will follow the crews throughout the footprint of the project as work progresses.
Once corrective work has been completed in the footprint of the project area (which includes parts of the 48th Ward), crews will transition to the sewer main replacement. The sewer main replacement will take approximately 6-8 weeks to install in each section of the project footprint. They will work in phases in each area, only shifting to a new area after replacing a sewer main on a leg in the impacted area.
Once the sewer pipe has been installed, the street will be temporarily restored with a concrete trench until they are able to completely restore the street with new asphalt. ADA-compliant sidewalk ramps will be repaired or installed where needed, along with repairs to damaged parkways and sidewalks. The final restoration of the street will include milling the surfacing, placing new asphalt, and prepainting the street markings. The project will not be considered complete until damaged sidewalks, parkways, and streets have been repaired in all areas where work is planned.
Our office is hosting a community meeting with the Department of Water Management and the contractors on Thursday, March 2, at 6 pm in the community room at Caroline Hedger, 6400 N. Sheridan.
For more information on the footprint of the project and to review an FAQ, visit the 49th Ward by clicking here.
​
February 17, 2023
Construction crews began to mobilize on Magnolia and Lakewood this week. Crews will begin pre-construction and corrective work in the area before transitioning to the sewer replacement. This means neighbors might begin to see more equipment and some excavation begin in the area. Crews may post "No Parking" signs in the impacted area as needed during work hours (generally 7 am to 4 pm). Crews will work to preserve as much parking as possible and will only post signs where crews are actively working; parking restrictions will follow the crews throughout the footprint of the project as work progresses.
Once corrective work has been completed in the footprint of the project area (which includes parts of the 48th Ward), crews will transition to the sewer main replacement. The sewer main replacement will take approximately 6-8 weeks to install in each section of the project footprint. They will work in phases in each area, only shifting to a new area after replacing a sewer main on a leg in the impacted area.
Once the sewer pipe has been installed, the street will be temporarily restored with a concrete trench until they are able to completely restore the street with new asphalt. ADA-compliant sidewalk ramps will be repaired or installed where needed, along with repairs to damaged parkways and sidewalks. The final restoration of the street will include milling the surfacing, placing new asphalt, and prepainting the street markings. The project will not be considered complete until damaged sidewalks, parkways, and streets have been repaired in all areas where work is planned.
Our office is working with the contractor to schedule a community meeting for neighbors so they have an opportunity to understand better the scope and timeline of the project as well as ask questions. Please keep your eye on this space for information on that meeting as well as updates throughout the duration of the project.
For more information on the footprint of the project and to review an FAQ, visit the 49th Ward by clicking here.
​
February 10, 2023
Construction crews have begun preparing the site for the sewer installation already, including marking the location for utility lines. Residents may start to notice construction equipment and materials placed in the area ahead of the project start date. Crews are beginning work on Highland Avenue in the 48th Ward.
When they finish the section in the 48th Ward, they will then transition to the 49th Ward to work on Magnolia, Lakewood, and Wayne. Each leg will take approximately 6-8 weeks to complete.
Once the pipe has been installed, the street will be temporarily restored with a concrete trench until they are able to completely restore the street with new asphalt. ADA-compliant sidewalk ramps will be repaired or installed where needed, along with repairs to damaged parkways and sidewalks. The final restoration of the street will include milling the surfacing, placing new asphalt, and prepainting the street markings. The project will not be considered complete until damaged sidewalks, parkways, and streets have been repaired in all areas where work is planned.
February 4, 2023
Construction crews have begun preparing the site for the sewer installation already, including marking the location for utility lines. Residents may start to notice construction equipment and materials placed in the area ahead of the project start date. Crews are beginning work on Highland Avenue in the 48th Ward.
When they finish the section in the 48th Ward, they will then transition to the 49th Ward to work on Magnolia, Lakewood, and Wayne. Each leg will take approximately 6-8 weeks to complete.
Once the pipe has been installed, the street will be temporarily restored with a concrete trench until they are able to completely restore the street with new asphalt. ADA-compliant sidewalk ramps will be repaired or installed where needed, along with repairs to damaged parkways and sidewalks. The final restoration of the street will include milling the surfacing, placing new asphalt, and prepainting the street markings. The project will not be considered complete until damaged sidewalks, parkways, and streets have been repaired in all areas where work is planned.
​
January 28, 2023
Construction crews have begun preparing the site for the sewer installation already, including marking the location for utility lines. Residents may start to notice construction equipment and materials placed in the area ahead of the project start date. Crews are beginning work on Highland Avenue in the 48th Ward.
When they finish the section in the 48th Ward, they will then transition to the 49th Ward to work on Magnolia, Lakewood, and Wayne. Each leg will take approximately 6-8 weeks to complete.
Once the pipe has been installed, the street will be temporarily restored with a concrete trench until they are able to completely restore the street with new asphalt. ADA-compliant sidewalk ramps will be repaired or installed where needed, along with repairs to damaged parkways and sidewalks. The final restoration of the street will include milling the surfacing, placing new asphalt, and prepainting the street markings. The project will not be considered complete until damaged sidewalks, parkways, and streets have been repaired in all areas where work is planned.
​
January 21, 2023
Construction crews have begun preparing the site for the sewer installation already, including marking the location for utility lines. Residents may start to notice construction equipment and materials placed in the area ahead of the project start date. Crews are beginning work on Highland Avenue in the 48th Ward.
When they finish the section in the 48th Ward, they will then transition to the 49th Ward to work on Magnolia, Lakewood, and Wayne. Each leg will take approximately 6-8 weeks to complete.
Once the pipe has been installed, the street will be temporarily restored with a concrete trench until they are able to completely restore the street with new asphalt. ADA-compliant sidewalk ramps will be repaired or installed where needed, along with repairs to damaged parkways and sidewalks. The final restoration of the street will include milling the surfacing, placing new asphalt, and prepainting the street markings. The project will not be considered complete until damaged sidewalks, parkways, and streets have been repaired in all areas where work is planned.