Pratt Avenue Resurfacing

Pratt Resurfacing.png
Winter '24 - Spring '25 Timeline
​
Neighbors, we have exciting news to share. This week, our office received notification from CDOT & contractors that Pratt Avenue from N. Western Ave. to N. Sheridan Rd. will be resurfaced beginning this year (during the winter of 2024), with a majority of the work scheduled for next year, spring 2025. Crews are tentatively scheduled to break ground beginning the week of November 25th, weather permitting. 

The work scheduled for this winter includes pavement patching, ADA sidewalk improvements, curb and gutter removal and replacement as needed for ADA and drainage compliance. To be clear, Pratt Avenue will not be ground and resurfaced this year. Only the above improvements will be made in winter 2025. 

The rest of the work including milling and paving the existing asphalt pavement, concrete bus pads, bike medians, and striping will be completed next spring. 

During construction, temporary “No Parking” signs will be periodically installed as required for each activity. These temporary signs will restrict parking during working hours for the completion of the work. The first phase of work (concrete work, ADA installation, and pothole filling) on Pratt Avenue is scheduled to be completed by December 31, 2024.

We are looking forward to this stretch of Pratt receiving some much-needed attention. Last week, Alderwoman Hadden met with CDOT representatives for a walk-through of Pratt Avenue to bring to crews' attention specific potholes and areas in need of fixing. Our office has been assured by CDOT that they will prioritize these locations per Alderwoman Hadden's instruction. 

If you have any questions about the scope or duration of this project, please reach out to the office via email at office@49thward.org or call 773-33-5796.