top of page

PN7439 Updates

PN7439 Map (1).png

June 24, 2023

Department of Water Management crews are working on lead service line replacements on Rogers from Ashland to Greenview. 

The sewer work at Rogers, Howard, and Greenview is complete, and the intersection has been reopened. However, it may have to close in a few weeks again to pour the concrete base. Crews project all concrete bases will be poured by the end of June. Once the base is poured, Chicago's in-house crews will return to work on water services. After that, crews can then begin to pour new asphalt and transition to the restoration phase of the project. 

June 18, 2023

The sewer work at Rogers, Howard, and Greenview is complete, and the intersection has been reopened. However, it may have to close in a few weeks again to pour the concrete base. Crews project all concrete bases will be poured by the end of June. Once the base is poured, Chicago's in-house crews will return to work on water services. After that, crews can then begin to pour new asphalt and transition to the restoration phase of the project. 

June 10, 2023

The sewer work at Rogers, Howard, and Greenview is complete, and the intersection has been reopened. However, it may have to close in a few weeks again to pour the concrete base. Crews project all concrete bases will be poured by the end of June. Once the base is poured, Chicago's in-house crews will return to work on water services. After that, crews can then begin to pour new asphalt and transition to the restoration phase of the project.

June 3, 2023

The sewer work at Rogers, Howard, and Greenview is complete, and the intersection has been reopened. However, it may have to close in a few weeks again to pour the concrete base. Crews project all concrete bases will be poured by the end of June. Once the base is poured, Chicago's in-house crews will return to work on water services. After that, crews can then begin to pour new asphalt and transition to the restoration phase of the project. 

May 27, 2023

The sewer work at Rogers, Howard, and Greenview is complete, and the intersection has been reopened. However, it may have to close in a few weeks again to pour the concrete base. Crews project all concrete bases will be poured by the end of June. Once the base is poured, Chicago's in-house crews will return to work on water services. After that, crews can then begin to pour new asphalt and transition to the restoration phase of the project. 

May 20, 2023

Rogers and Howard reopened to two-way traffic this week. Traffic on Greenview north of Rogers is scheduled to reopen on Friday. 

Crews are working on the sewer installation on Birchwood. As soon as the new sewer pipe is installed, a concrete base will be poured. 

May 13, 2023

ComEd is working at the intersection of Rogers, Greenview, and Howard to restore its conduit ducts. This has caused a delay in the reopening of the intersection, and it will remain closed beyond May 1. As soon as ComEd finished up its work, crews will be able to pour a concrete base to reopen the intersection. Please continue to plan your commute around the closure of this major intersection.

On Friday, crews began pouring the concrete base on Greenfiwe south of Howard. The sewer installation on Greenview was completed this week, and crews will pour the concrete base some time next week weather permitting. 

May 6, 2023

ComEd is working at the intersection of Rogers, Greenview, and Howard to restore its conduit ducts. This has caused a delay in the reopening of the intersection, and it will remain closed beyond May 1. As soon as ComEd finished up its work, crews will be able to pour a concrete base to reopen the intersection. Please continue to plan your commute around the closure of this major intersection.

On Monday, the water crews will perform a water main cut and cap at Greenview and Birchwood. The sewer installation on Greenview is ongoing.

April 29, 2023

ComEd is working at the intersection of Rogers, Greenview, and Howard to restore its conduit ducts. This has caused a delay in the reopening of the intersection, and it will remain closed beyond May 1. As soon as ComEd finished up its work, crews will be able to pour a concrete base to reopen the intersection. Please continue to plan your commute around the closure of this major intersection.

Water crews are continuing to install the sewer pipe on Greenview toward Birchwood. After the sewer pipe is installed in this area, crews will shift to begin working on Greenview just north of Rogers.

April 23, 2023

Crews are continuing to install the sewer pipe and sewer structures at the intersection of Rogers, Greenview, and Howard. Birchwood Avenue at Ashland reopened to traffic this week; eastbound Howard is projected to be reopened to traffic on May 1.

April 14, 2023

Crews are continuing to install the sewer pipe and sewer structures at the intersection of Rogers, Greenview, and Howard. Birchwood Avenue at Ashland reopened to traffic this week; eastbound Howard is projected to be reopened to traffic on May 1.

April 7, 2023

Crews are continuing to install the sewer pipe and sewer structures at the intersection of Rogers, Greenview, and Howard. Birchwood Avenue at Ashland reopened to traffic this week; eastbound Howard is projected to be reopened to traffic on May 1.

April 1, 2023

Crews are pouring a concrete base on Rogers from Ashland to Greenview. On Wednesday, crews will perform a water main cut and cap at the intersection of Rogers and Greenview. Birchwood east of Ashland will remain closed to traffic over the weekend as the new concrete trench cures. Other traffic controls in the impacted area remain. 

March 24, 2023

New traffic control stages have been set up at the intersection of Rogers and Greenview. The south leg of Greenview has closed at Howard for work. The contractor is performing a water main cut and cap at the intersection of Rogers and Greenview and will continue working on installing the new sewer pipes. 

March 17, 2023

New traffic control stages have been set up at the intersection of Rogers and Greenview. The south leg of Greenview has closed at Howard for work. The contractor is performing a water main cut and cap at the intersection of Rogers and Greenview and will continue working on installing the new sewer pipes. 

March 11, 2023

The water main reconnection at Rogers and Ashland is scheduled for next Wednesday. Sewer work is ongoing on the Rogers. The northbound lane closure on Rogers northbound from Ashland to Greenview is still in place so crews can safely work on the sewer replacement. A detour of the area is set up in direction of going N. Clark to W. Touhy to N. Sheridan. The closure and detour may result in delays for motorists, so plan your commute accordingly. 

March 4, 2023

Sewer work is ongoing on the Rogers. The northbound lane closure on Rogers northbound from Ashland to Greenview is still in place so crews can safely work on the sewer replacement. A detour of the area is set up in direction of going N. Clark to W. Touhy to N. Sheridan. The closure and detour may result in delays for motorists, so plan your commute accordingly. 

February 24, 2023

Sewer work is ongoing on the Rogers. The northbound lane closure on Rogers northbound from Ashland to Greenview is still in place so crews can safely work on the sewer replacement. A detour of the area is set up in direction of going N. Clark to W. Touhy to N. Sheridan. The closure and detour may result in delays for motorists, so plan your commute accordingly. 

February 17, 2023

Crews are beginning work on backfilling the Earth Retention System at Rogers and Ashland. The northbound lane closure on Rogers northbound from Ashland to Greenview is still in place so crews can safely work on the sewer replacement. A detour of the area is set up in direction of going N. Clark to W. Touhy to N. Sheridan. The closure and detour may result in delays for motorists, so plan your commute accordingly. 

February 10, 2023

The lane closure on Rogers northbound from Ashland to Greenview is still in place so crews can safely work on the sewer replacement. A detour of the area is set up in direction of going N. Clark to W. Touhy to N. Sheridan. The closure and detour may result in delays for motorists, so plan your commute accordingly. 

February 4, 2023

Crews will implement a lane closure on Rogers northbound from Ashland to Greenview so they can safely work on the sewer replacement. A detour of the area will be set up in direction of going N. Clark to W. Touhy to N. Sheridan. The closure and detour may result in delays for motorists, so plan your commute accordingly. Once the lane closure is in place, crews will be able to begin work on the sewer installation. 

January 28, 2023

Crews plan to perform a water main cut and cap at Rogers and Ashland next week. Beginning on Friday, February 2, crews will set up a lane closure on Rogers northbound from Ashland to Greenview. The closure may include detours and delays for motorists, so plan your commute accordingly. Once the lane closure is in place, crews will be able to begin work on the sewer installation. 

January 21, 2023

Crews mobilized on site this week. However, there is a water main that must be temporarily removed and replaced to allow for the new sewer to be constructed. While sewer plans accounted for the water main, crews found that the configuration in the field is different than what was in the plans. With an infrastructure that is over 100 years old, crews do their best to go off of any records of what is underground or best guesses based on what they've encountered in other areas. Sometimes there are discrepancies once the ground is open. This means that crews now have to revise their plan in order to proceed with the sewer work. Crews hope to be back on site in the next week or two to continue with the sewer work. 

January 14, 2023

Crews continue to await for approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back from its original start date in early September. Crews anticipate having a new permit issued on Monday and for the project to commence on the week of January 16

January 7, 2023

Crews continue to await for approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back from its original start date in early September. Crews anticipate having a new permit issued on Monday and for the project to commence on the week of January 16

December 23, 2022

Crews continue to await for approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back from its original start date in early September. Crews now expect the project to start some time in January 2023. 

December 17, 2022

Crews continue to await for approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back from its original start date in early September. Crews now expect the project to start some time in January 2023. 

December 10, 2022

Crews are awaiting approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back from its original start date in early September. Crews believe that the issues are close to a resolution and that work can begin some time this month. 

December 3, 2022

Crews are awaiting approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back from its original start date in early September. Crews believe that the issues are close to a resolution and that work can begin some time this month. 

November 18, 2022

Crews are awaiting approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back slightly.

November 11, 2022

Crews are awaiting approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back slightly.

November 5, 2022

Crews are awaiting approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back slightly.

October 29, 2022

Crews are awaiting approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back slightly.

October 21, 2022

Crews are awaiting approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back slightly.

October 15, 2022

Crews are awaiting approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back slightly.

October 7, 2022

Crews are awaiting approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back slightly.

October 1, 2022

Crews are awaiting approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back slightly.

September 25, 2022

Crews are awaiting approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back slightly.

September 16, 2022

Crews are awaiting approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back slightly.

September 10, 2022

Crews are awaiting approval from the Office of Underground Coordination. Once they receive that approval, permits will be issued for the sewer main replacement. This has caused the start date of the project to be pushed back slightly.

September 3, 2022

The project is scheduled to begin tentatively on Tuesday, September 6

August 27, 2022

The project is scheduled to begin tentatively on Tuesday, September 6

August 20, 2022

The project is scheduled to begin tentatively on Tuesday, September 6

bottom of page